BlueSpine is involved in the assessment and project management of the Septentrion Bridge in the Var.

The structure: A box girder bridge with reinforced concrete beams located in Port Grimaud (83) and dating from 1969.
The assignment: Assessment | Project Management (PC)
The client: Syndicat Cité Lacustre de Port Grimaud
Our involvement: BlueSpine is involved in the rehabilitation of the Septentrion Bridge in the famous Cité Lacustre of Port Grimaud. The studies carried out by our teams were as follows:
- Assessment of corrosion throughout the reinforced concrete section of the bridge
- Recommendation of the most suitable treatment for the rehabilitation of the structure
- Preliminary design of the chosen treatment solution
- Project management: Preliminary design / Detailed design / Construction documents / Final design / Technical supervision / Handover.
- Inline corrections